Thai Ha Industrial Park
Location ♦ Province: Hanam (GRDP 2023 of US$2.1 billion and RDP per capita in 2023 of $US3,900; economy structure with 70% of industry and construction)

♦ Land type: rural

♦ 75 km to Hanoi Capital Center

♦ 21.2 km to Phu Ly City Center

♦ 85 km to Noi Bai International Airport

♦ 107 km to Hai Phong Seaport

♦ 17km from Cau Gie Ninh Binh Highway

♦ 270km to Vietnam – China Border Gate

Total Land area 100ha (industrial land area of 72.5ha) for phase I (already completed infrastructure)

100 ha (industrial land area of 74.82ha) for phase 2 (land clearance is on-going to prepare for infrastructure construction)

Leasing Term 15/11/2069
Minimum Lease area TBA
Investment Field Prioritized sectors: Mechanical engineering, assembly, automobiles, motorcycles, Electrical, electronics, telecommunications, information technology, supporting industries, new materials, Processing, preservation of agricultural products, food, beverages, milk

Restricted sectors: Industries that cause environmental pollution through the process of production and discharge (For examples: textile dyeing industry, chemical industry, feed manufacture, etc)

Construction Information Construction rate: 60%

Workshop buildings: maximum 3 floors

Office buildings: maximum 3 floors

Height Limit of Building: 45m (but can be higher for special case)

Setback: setback of building is 6-10m from the adjacent road boundary and 3.5m from the next plot

Road width Main road: 46m

Branch road: 28m – 21.25m – 18.25m

Operation Status Completed the essential infrastructure system
Occupancy Rate 40% currently for phase 1
Leasing Fee US$85-90/m2 (still negotiable)
Operating Fee ♦ Management fee: 11,600VND (0.5USD)/m2 /year

♦ Fresh water cost: 11,500VND/m3

♦ Wastewater treatment fee (From Level B to A): 11,000 VND ().478USD)/m3

♦ Electricity cost: same price as regulated by EVN (Normal hour: 0.063 USD Low hour: 0.039 USD Peak hour: 0.11USD)

♦ Waste treatment fee: price provided by waste treatment unit

Minimum Wage and Labor Force Minimum Salary Zone 3 (approximately equivalent to US$161/person/month since July 2024 and might be increased about 6-10% by the order of National Assembly every 2-3 years)

Population of 885 thousand people (60% at working age) and over 95,000 well educated/trained workers available in the labor market

17 local universities, colleges and training institutions in the province with over 18,000 students graduated annually that can be available for recruitment